Unipol SAI
Construction of the Unipol Assicurazioni data centre
Adaptation and modification works with expansion of the mechanical, electrical and electrotechnical systems specific to the new Data Centre. Installation of air conditioning, lighting, electrical power, data transmission, special electrical and fire prevention/fire protection systems in the office block.
Strengths
The work on the building involved complex and significant engineering of both electrical and mechanical systems. This work was carried out in various indoor and outdoor areas.
L’edificio ha ottenuto la certificazione TIER di livello IV dall'UPTIME INSTITUTE, il principale creatore e gestore mondiale di standard di certificazione per data center in termini di sostenibilità ed efficienza operativa.
Keynumbers
6.935 m²
Total area of intervention
Context
In 2013, a major project was launched to manage the effects of climate change. This ongoing project involves the direct involvement of the Technical Department of Unipol Assicurazioni and, since 2014, of UnipolSai.
The aim is to promote resilience to change.
Following the acquisition of the former Premafin Group, the company decided to circumvent the risk of duplicating the number of servers by dismantling the existing IT infrastructure and building a completely new one.
The latter will adopt much more advanced technologies to reduce the energy consumption of both the systems themselves and the cooling systems in the installation premises.
Due to the nature of the business and the IT equipment used by employees and data centres, this area has a considerable impact on energy consumption and therefore on greenhouse gas emissions.
The design takes into account the priorities set out in the Unipol Group's three-year Sustainability Plan (2015): reducing energy and water consumption and minimising paper-based procedures and documents.
The purpose of these interventions was to install the mechanical and electrical systems necessary to ensure the perfect and complete operation and continuity of the IT systems of the new Data Centre.
Challenges
Intervention
The project was divided into two lots:
Lot 1
Adaptation of the existing building to complete the new Data Processing Centre (DPC);
Lot 2
Works inside and outside the main building to complete the office block.
Realisation
MECHANICAL SYSTEMS
Mechanical systems for air conditioning, water, sanitation, drainage, air conditioning fluids, fire prevention and gas distribution have been installed to serve the new Data Centre and offices. The aim is to ensure the protection and full operability of IT equipment. The systems include:
- Cooling units for chilled water for the Data Centre and electrical rooms;
- Chilled water distribution with dual branch for operational continuity;
- Pumping unit dedicated to each branch;
- Under-type precision air conditioners dedicated to air conditioning each room in the data centre;
- External air intake and exhaust sections dedicated to the proper functioning of the system in free-cooling mode;
- Fire protection system with automatic shutdown to protect the Data Centre and electrical equipment rooms;
- Water pumping station with dual rainwater pumping system to protect the containment tank of the rotating UPS units.
ELECTRICAL SYSTEMS
Highly reliable electrical systems with double radial architecture and full redundancy were supplied to support the operational continuity of IT equipment even in the event of failure. The main activities included:
- Primary certification, connection and energy activation;
- Telephone lines and main input;
- MV/LV switchboards and transformers;
- UPS systems, generators and low and medium voltage switchboards;
- Primary and secondary power distribution;
- IT, mechanical and service system power supply;
- Ordinary and emergency lighting;
- Generator sets;
- Earthing, equipotential and atmospheric discharge systems;
- Smoke detection, flood prevention, automatic system shutdown;
- Evacuation sirens, data systems, intrusion alarm, access control, CCTV;
- BMS, consumption monitoring and CED area control (DCIM).
Download
Gallery
Tutte le foto (3)
Case Study

La Casa di Leonardo
Cefla ha completato il data center 'La Casa di Leonardo' a Bologna, ottenendo certificazioni di...

Torre Unipol, EPC Contracting
Cefla ha trasformato Torre Unipol a Milano con soluzioni tecnologiche avanzate, sostenibilità e un...

Torre Allianz, EPC Contracting
Scopri come Cefla ha realizzato gli impianti meccanici della Torre Allianz a Milano, garantendo...

Galleria degli Uffizi
Cefla ha modernizzato gli impianti delle Gallerie degli Uffizi, garantendo efficienza energetica e...

Teatro alla Scala
Restauro impianti Teatro alla Scala: integrazione invisibile, sicurezza, efficienza energetica e...

Cefla Gest
Scopri come Cefla GEST ottimizza la gestione e manutenzione degli impianti industriali, garantendo...

Bassi Business Park
Riqualificazione sostenibile e tecnologica del Bassi Business Park a Milano, con focus su...

FICO Eataly World
Scopri come Cefla ha contribuito alla realizzazione di FICO Eataly World con soluzioni...

Poste Italiane
Realizzazione del data center centralizzato di Poste Italiane, con certificazione TIER IV e...

Unipol SAI De Castillia 23
Scopri come Cefla ha trasformato De Castillia 23 a Milano in un moderno ed efficiente edificio per...
News

Cefla participates in Agribiogas 2025
04 July 2025
AgriBiogas 2025 offers an agenda aimed at delving into the future of the biogas and biomethane system, between critical issues to be overcome and opportunities to be seized, untangling the PNRR and the Ecological Practices Decree.

Data Center Nation 2025
04 July 2025
On Wednesday, April 2, 2025, we will participate in Data Center Nation at the Allianz MiCo - Milano Convention Centre - one of the main reference events in Italy for the #Datacenter industry.

Key Energy 2025 Rimini
04 July 2025
We will be at KEY 2025, the benchmark event for energy transition. Discover our solutions for cogeneration, fuel cells and energy efficiency.
Find the perfect solution for your business