Unipol SAI

Construction of the Unipol Assicurazioni data centre
Customer Unipol Assicurazioni
Where Bologna
Solution General Contracting
Sector Data center
Target achieved Conversion of the building into a new state-of-the-art data processing centre.

Adaptation and modification works with expansion of the mechanical, electrical and electrotechnical systems specific to the new Data Centre. Installation of air conditioning, lighting, electrical power, data transmission, special electrical and fire prevention/fire protection systems in the office block.

Strengths

The work on the building involved complex and significant engineering of both electrical and mechanical systems. This work was carried out in various indoor and outdoor areas.

L’edificio ha ottenuto la certificazione TIER di livello IV dall'UPTIME INSTITUTE, il principale creatore e gestore mondiale di standard di certificazione per data center in termini di sostenibilità ed efficienza operativa.




Keynumbers

6.935 m²

Total area of intervention

Context

In 2013, a major project was launched to manage the effects of climate change. This ongoing project involves the direct involvement of the Technical Department of Unipol Assicurazioni and, since 2014, of UnipolSai.
The aim is to promote resilience to change.
Following the acquisition of the former Premafin Group, the company decided to circumvent the risk of duplicating the number of servers by dismantling the existing IT infrastructure and building a completely new one.
The latter will adopt much more advanced technologies to reduce the energy consumption of both the systems themselves and the cooling systems in the installation premises.
Due to the nature of the business and the IT equipment used by employees and data centres, this area has a considerable impact on energy consumption and therefore on greenhouse gas emissions.
The design takes into account the priorities set out in the Unipol Group's three-year Sustainability Plan (2015): reducing energy and water consumption and minimising paper-based procedures and documents.

 

The purpose of these interventions was to install the mechanical and electrical systems necessary to ensure the perfect and complete operation and continuity of the IT systems of the new Data Centre.


Challenges

The technological systems supporting the equipment guarantee reliability and energy efficiency, aspects that have been given top priority in the selection and sizing of the materials and equipment installed in the plant.

Intervention

The project was divided into two lots:

Lot 1

Adaptation of the existing building to complete the new Data Processing Centre (DPC);

Lot 2

Works inside and outside the main building to complete the office block.

 

 


Realisation

 

MECHANICAL SYSTEMS

Mechanical systems for air conditioning, water, sanitation, drainage, air conditioning fluids, fire prevention and gas distribution have been installed to serve the new Data Centre and offices. The aim is to ensure the protection and full operability of IT equipment. The systems include:

  • Cooling units for chilled water for the Data Centre and electrical rooms;
  • Chilled water distribution with dual branch for operational continuity;
  • Pumping unit dedicated to each branch;
  • Under-type precision air conditioners dedicated to air conditioning each room in the data centre;
  • External air intake and exhaust sections dedicated to the proper functioning of the system in free-cooling mode;
  • Fire protection system with automatic shutdown to protect the Data Centre and electrical equipment rooms;
  • Water pumping station with dual rainwater pumping system to protect the containment tank of the rotating UPS units.

ELECTRICAL SYSTEMS

Highly reliable electrical systems with double radial architecture and full redundancy were supplied to support the operational continuity of IT equipment even in the event of failure. The main activities included:

  • Primary certification, connection and energy activation;
  • Telephone lines and main input;
  • MV/LV switchboards and transformers;
  • UPS systems, generators and low and medium voltage switchboards;
  • Primary and secondary power distribution;
  • IT, mechanical and service system power supply;
  • Ordinary and emergency lighting;
  • Generator sets;
  • Earthing, equipotential and atmospheric discharge systems;
  • Smoke detection, flood prevention, automatic system shutdown;
  • Evacuation sirens, data systems, intrusion alarm, access control, CCTV;
  • BMS, consumption monitoring and CED area control (DCIM).


Case Study

Show all
La Casa di Leonardo
EPC Contracting

La Casa di Leonardo

Cefla ha completato il data center 'La Casa di Leonardo' a Bologna, ottenendo certificazioni di...

Torre Unipol, EPC Contracting
EPC Contracting

Torre Unipol, EPC Contracting

Cefla ha trasformato Torre Unipol a Milano con soluzioni tecnologiche avanzate, sostenibilità e un...

Torre Allianz, EPC Contracting
EPC Contracting

Torre Allianz, EPC Contracting

Scopri come Cefla ha realizzato gli impianti meccanici della Torre Allianz a Milano, garantendo...

Galleria degli Uffizi
EPC Contracting

Galleria degli Uffizi

Cefla ha modernizzato gli impianti delle Gallerie degli Uffizi, garantendo efficienza energetica e...

Teatro alla Scala
EPC Contracting

Teatro alla Scala

Restauro impianti Teatro alla Scala: integrazione invisibile, sicurezza, efficienza energetica e...

Cefla Gest
EPC Contracting

Cefla Gest

Scopri come Cefla GEST ottimizza la gestione e manutenzione degli impianti industriali, garantendo...

Bassi Business Park
EPC Contracting

Bassi Business Park

Riqualificazione sostenibile e tecnologica del Bassi Business Park a Milano, con focus su...

FICO Eataly World
EPC Contracting

FICO Eataly World

Scopri come Cefla ha contribuito alla realizzazione di FICO Eataly World con soluzioni...

Poste Italiane
EPC Contracting

Poste Italiane

Realizzazione del data center centralizzato di Poste Italiane, con certificazione TIER IV e...

Unipol SAI De Castillia 23
EPC Contracting

Unipol SAI De Castillia 23

Scopri come Cefla ha trasformato De Castillia 23 a Milano in un moderno ed efficiente edificio per...

Find the perfect solution for your business

 

Prefooter background
We create. You live