CED Crif

Construction of the Crif data centre
Customer Crif, Schneider Electric. VEM Sistemi
Where Castel San Pietro Terme - Varignana (BO)
Solution General Contracting
Sector Data center
Target achieved Building certification according to the protocol LEED® Building Design and Construction for New Construction v4

Cefla managed the installation and commissioning of the mechanical systems, supervising the construction sites of Schneider Electric and VEM Sistemi.

Strengths

coordination of players in the field, as the project leader

design and construction of technological systems



partnership with the customer to achieve the target in an impressively short timeframe


Key Numbers

2x347 Kw

Installed cooling capacity

3.000 mc/h

Air flow rate

82x1.000 kVA x 2

Installed electrical power

1.250 sqm

Area of intervention

Background

CRIF is a company specialising in credit information and business information systems, outsourcing and processing services, and credit solutions. Founded in Bologna in 1988, it now operates globally and one of its leading technology centres is located in one of the buildings that make up the “Palazzo di Varignana” complex, now also a resort and spa, the result of the renovation of an ancient villa dating back to 1705. In this setting, the building that houses CRIF's technology centre is connected to the administrative building by an underground tunnel. The operational rooms are arranged along a loop corridor containing the data centres, carrier rooms, tape room, fire extinguishing system rooms, UPS rooms and rooms dedicated to special systems. Outside the perimeter corridor are the battery rooms, transformer rooms, mechanical system control room and storage rooms. Outside this complex, supporting the technology hub, are the areas housing the generator sets and chillers.

The installation and construction of the data centre for Crif took place in a highly responsible and complex construction site environment and was brilliantly coordinated by our designers and technicians.


Challenges

  • Integration with existing architecture
    Designing technological systems that integrate seamlessly with the architecture of the buildings, preserving the aesthetics and functionality of spaces.
  • High energy efficiency standards
    Ensuring plant engineering solutions that meet the highest standards of energy efficiency and environmental sustainability.
  • Tight deadlines
    Completing work in a short time frame, coordinating with other construction site activities.

Project Tasks

Construction of a data centre with the aim of obtaining the following certifications:

• Building certification according to the LEED® Building Design and Construction for New Construction v4 protocol with SILVER level.

The project is registered with the Green Building Certification Institute, the independent third-party organisation that certifies the building. The LEED® v4 NC protocol refers to buildings whose design and construction parameters fall within specific criteria for health, energy efficiency and low environmental impact.

Uptime Institute Tier IV certification for the Data Centre.

The Tier classification system provides the data centre industry with a consistent method for comparing unique and customised facilities based on expected site infrastructure performance or uptime. It also allows companies to align their data centre infrastructure investments with specific business growth and technology strategies.


Implementation

The building that houses the data centre has been equipped with the following mechanical systems:
• Water and sanitation system
• Air conditioning system
• Ventilation system
• Automatic gas extinguishing system
• Post-gas discharge air extraction system
• Regulation and supervision system
• Drainage and sewerage system
The electrical systems installed within the same building to support the operation of the data centre are:
• Power supply
• Special systems: fire detection and extinguishing, flood prevention, structured cabling
• Supervision system

 


Case Study

Show all
La Casa di Leonardo
EPC Contracting

La Casa di Leonardo

Cefla ha completato il data center 'La Casa di Leonardo' a Bologna, ottenendo certificazioni di...

Torre Unipol, EPC Contracting
EPC Contracting

Torre Unipol, EPC Contracting

Cefla ha trasformato Torre Unipol a Milano con soluzioni tecnologiche avanzate, sostenibilità e un...

Torre Allianz, EPC Contracting
EPC Contracting

Torre Allianz, EPC Contracting

Scopri come Cefla ha realizzato gli impianti meccanici della Torre Allianz a Milano, garantendo...

Galleria degli Uffizi
EPC Contracting

Galleria degli Uffizi

Cefla ha modernizzato gli impianti delle Gallerie degli Uffizi, garantendo efficienza energetica e...

Teatro alla Scala
EPC Contracting

Teatro alla Scala

Restauro impianti Teatro alla Scala: integrazione invisibile, sicurezza, efficienza energetica e...

Cefla Gest
EPC Contracting

Cefla Gest

Scopri come Cefla GEST ottimizza la gestione e manutenzione degli impianti industriali, garantendo...

Bassi Business Park
EPC Contracting

Bassi Business Park

Riqualificazione sostenibile e tecnologica del Bassi Business Park a Milano, con focus su...

FICO Eataly World
EPC Contracting

FICO Eataly World

Scopri come Cefla ha contribuito alla realizzazione di FICO Eataly World con soluzioni...

Poste Italiane
EPC Contracting

Poste Italiane

Realizzazione del data center centralizzato di Poste Italiane, con certificazione TIER IV e...

Unipol SAI De Castillia 23
EPC Contracting

Unipol SAI De Castillia 23

Scopri come Cefla ha trasformato De Castillia 23 a Milano in un moderno ed efficiente edificio per...

Find the perfect solution for your business

Prefooter background
We create. You live