Generali Real Estate
Construction of the Generali Immobiliare data centre
Assicurazioni Generali's data centres and their uninterrupted service continuity are vital to the company's core business. The project involved the completion and preparation of all systems in order to maximise energy savings.
Strengths
For all systems serving the Data Centre or areas associated with its operation, 100% redundancy has been maintained for equipment and 50% for water distribution (via a third backup pipe).
A network of measuring instruments has been set up to monitor the various parameters on the Data Centre control panels. Monitoring covers not only voltage, current and power, but also parameters such as harmonic distortion and voltage drops, in order to highlight any power supply problems affecting the Data Centre machines.
Key Numbers
5.000 kW
installed electrical power
1.525 kW
installed cooling capacity
49.536 m3/h
air flow
Background
All work was carried out without interrupting the operation of existing equipment.
Challenges
Efforts were also made to achieve the lowest possible PUE (Power Usage Effectiveness) value, compatible with the climatic characteristics of the site, while preserving existing and still efficient equipment as much as possible.
Project Tasks
The technological systems supporting the equipment must guarantee system reliability and energy efficiency, aspects which were given top priority in the selection and sizing of the materials and equipment installed at the site.
Implementation
New IT equipment was installed, with a maximum power consumption of approximately 1,000 kW, to allow for future developments.
This involved upgrading the systems in the rooms housing the IT equipment, both in terms of available electrical power and environmental cooling capacity. To achieve this, work was carried out on the air conditioning systems (both in the IT rooms and in auxiliary technical areas such as UPS technical rooms, etc.) to achieve a proportional reduction in energy consumption. Similarly, the focus was on reducing the energy costs arising from self-consumption by the UPS units. This was achieved by installing four latest-generation units with offline operating mode capable of keeping the emergency power supply system on standby, while reducing consumption from the current 6-8% of nominal load to approximately 1%. Thanks to new rapid response electronic technology, it is possible to switch from offline to online configuration in an extremely short time (2-3 milliseconds) without interrupting the IT system's power supply and, at the same time, avoiding the level of consumption typically associated with traditional uninterruptible power supplies (UPS).
Given the substantial absence of personnel and latent heat load, the heat load inside data centres is generally only of the “sensitive” type. The use of standard air conditioning units (which usually operate with cooling water flow and return temperatures of 7°C and 12°C - respectively) causes excessive dehumidification of the cooling air. This requires subsequent rehumidification of the air (to avoid electrostatic charges that could accumulate if the air is too dry), with considerable energy waste. In these rooms, however, it is possible to significantly increase the operating temperatures of the chilled water, with supply and return values of 12°C and 17°C respectively, thus minimising the dehumidifying effect of the cold coil. This led to the design decision to separate the data centre circuits from those of the offices, as this will subsequently allow the different areas, used for different purposes, to use water circuits at different temperatures, with considerable energy savings.
Download
Tutte le foto (0)
Case Study

Unipol Tower Facility Management
Comprehensive and sustainable management of Unipol Tower with advanced technologies and strategies...

Prysmian
Cefla manages facility management at Prysmian's Milan headquarters, ensuring operational...

Centergross
Integrated management of 1 million m² for Centergross by Cefla, with sustainable solutions and...

Prometeia, Facility Management
Learn how Cefla manages Prometeia's headquarters with a total facility management service, ensuring...

Allianz Tower, Facility Management
Integrated and sustainable management of the Allianz Tower in Milan, with advanced facility...

Generali Real Estate
Realization of Generali Real Estate's data center in Mogliano Veneto to maximize energy savings and...

Unipol Group real estate asset management
Gestione del patrimonio immobiliare di Unipol con Cefla: servizio completo, efficienza energetica e...
News

Cefla and Unica Ingegneria launch Pre-vision: sustainability generates efficiency with a predictive approach
02 September 2025
Through the development of en.vision, it aims to make a difference for companies that want to invest in concrete energy efficiency, optimization, decarbonization, cybersecurity, and resource preservation projects.

58 week-long works, no inconvenience - the Astalli Substation project in downtown Rome
02 September 2025
Cefla Engineering enhances fire safety at the historic Astalli Substation in Rome, ensuring uninterrupted electricity supply during extensive year-long renovations.

Networked Services Tour 2025: Networks in security, projects that look to the future
01 September 2025
Learn how Cefla transforms historic infrastructure into sustainable energy networks and the use of AI for predictive water maintenance at the Networked Services Tour 2025.
Find the perfect solution for your business