Generali Real Estate
Construction of the Generali Immobiliare data centre
Assicurazioni Generali's data centres and their uninterrupted service continuity are vital to the company's core business. The project involved the completion and preparation of all systems in order to maximise energy savings.
Strengths
For all systems serving the Data Centre or areas associated with its operation, 100% redundancy has been maintained for equipment and 50% for water distribution (via a third backup pipe).
A network of measuring instruments has been set up to monitor the various parameters on the Data Centre control panels. Monitoring covers not only voltage, current and power, but also parameters such as harmonic distortion and voltage drops, in order to highlight any power supply problems affecting the Data Centre machines.
Key Numbers
5.000 kW
installed electrical power
1.525 kW
installed cooling capacity
49.536 m3/h
air flow
Background
All work was carried out without interrupting the operation of existing equipment.
Challenges
Efforts were also made to achieve the lowest possible PUE (Power Usage Effectiveness) value, compatible with the climatic characteristics of the site, while preserving existing and still efficient equipment as much as possible.
Project Tasks
The technological systems supporting the equipment must guarantee system reliability and energy efficiency, aspects which were given top priority in the selection and sizing of the materials and equipment installed at the site.
Implementation
New IT equipment was installed, with a maximum power consumption of approximately 1,000 kW, to allow for future developments.
This involved upgrading the systems in the rooms housing the IT equipment, both in terms of available electrical power and environmental cooling capacity. To achieve this, work was carried out on the air conditioning systems (both in the IT rooms and in auxiliary technical areas such as UPS technical rooms, etc.) to achieve a proportional reduction in energy consumption. Similarly, the focus was on reducing the energy costs arising from self-consumption by the UPS units. This was achieved by installing four latest-generation units with offline operating mode capable of keeping the emergency power supply system on standby, while reducing consumption from the current 6-8% of nominal load to approximately 1%. Thanks to new rapid response electronic technology, it is possible to switch from offline to online configuration in an extremely short time (2-3 milliseconds) without interrupting the IT system's power supply and, at the same time, avoiding the level of consumption typically associated with traditional uninterruptible power supplies (UPS).
Given the substantial absence of personnel and latent heat load, the heat load inside data centres is generally only of the “sensitive” type. The use of standard air conditioning units (which usually operate with cooling water flow and return temperatures of 7°C and 12°C - respectively) causes excessive dehumidification of the cooling air. This requires subsequent rehumidification of the air (to avoid electrostatic charges that could accumulate if the air is too dry), with considerable energy waste. In these rooms, however, it is possible to significantly increase the operating temperatures of the chilled water, with supply and return values of 12°C and 17°C respectively, thus minimising the dehumidifying effect of the cold coil. This led to the design decision to separate the data centre circuits from those of the offices, as this will subsequently allow the different areas, used for different purposes, to use water circuits at different temperatures, with considerable energy savings.
Download
Tutte le foto (0)
Case Study

La Casa di Leonardo
Cefla ha completato il data center 'La Casa di Leonardo' a Bologna, ottenendo certificazioni di...

Torre Unipol, EPC Contracting
Cefla ha trasformato Torre Unipol a Milano con soluzioni tecnologiche avanzate, sostenibilità e un...

Pizzoli
Progetto innovativo di Cefla e Pizzoli: un Energy Hub sostenibile per ottimizzare consumo...

NOVA by Cefla a Imola
Prima installazione europea di cogenerazione a fuel cell da Cefla a Imola: alta efficienza...

Torre Allianz, Facility Management
Gestione integrata e sostenibile della Torre Allianz a Milano, con soluzioni avanzate di Cefla per...

Torre Allianz, EPC Contracting
Scopri come Cefla ha realizzato gli impianti meccanici della Torre Allianz a Milano, garantendo...

Galleria degli Uffizi
Cefla ha modernizzato gli impianti delle Gallerie degli Uffizi, garantendo efficienza energetica e...

Unipol Assicurazioni a Torino
Riqualificazione sostenibile della sede Unipol a Torino con tecnologie avanzate di Cefla,...

Teatro alla Scala
Restauro impianti Teatro alla Scala: integrazione invisibile, sicurezza, efficienza energetica e...

Prysmian
Cefla gestisce il facility management della sede Prysmian a Milano, garantendo efficienza...
News

Cefla participates in Agribiogas 2025
04 July 2025
AgriBiogas 2025 offers an agenda aimed at delving into the future of the biogas and biomethane system, between critical issues to be overcome and opportunities to be seized, untangling the PNRR and the Ecological Practices Decree.

Data Center Nation 2025
04 July 2025
On Wednesday, April 2, 2025, we will participate in Data Center Nation at the Allianz MiCo - Milano Convention Centre - one of the main reference events in Italy for the #Datacenter industry.

Key Energy 2025 Rimini
04 July 2025
We will be at KEY 2025, the benchmark event for energy transition. Discover our solutions for cogeneration, fuel cells and energy efficiency.
Find the perfect solution for your business
